Water Main Replacement
Preconstruction Notification
August 15, 2023
As part of the upcoming Main Street water main replacement project, this notice is to inform and outline the type and area of work. The water main replacement will be from the intersection of Pennsylvania Avenue to Longwell Avenue, shown in the image below. The map shows the estimated start and finish dates for each phase of construction. This is an estimated timeline and can be affected by several variables. Updates will be posted on this page.
This project will replace an existing water main and service connections in the outlined area. The new service line will be replaced to the existing shutoff valves. This work will be done in 8 phases and total time of construction will be approximately 220 days. Construction is scheduled to start on September 14, 2023.
Key information:
1. Workdays will be Monday to Friday, 7:00 am to 5:00 pm.
2. All roads will remain open with two-way traffic during construction.
3. No parking areas will be kept to a minimum.
4. Sidewalks will remain open.
5. Water disruptions will be minimal and coordinated with owners.
Mayor Becker will hold a community meeting for the public at the City Administration building located at 45 w. Main Street on August 28, 2023, at 5:30 pm. Mayor and city staff will discuss the project and be available for any questions afterwards.
Contacts for this project will be Deputy Director John Dick and Economic Development Coordinator Melissa Thorn our contact information is below. Please direct any concerns or questions about project construction to Mr. Dick.
John C. Dick Melissa Thorn
Deputy Director of Public Works Economic Development Coordinator
Jdick@westminsterMD.gov mthorn@westminsterMD.gov
443-909-9622 410-848-5294
The water main replacement will be from the intersection of Pennsylvania Avenue to Longwell Avenue, shown in the image below.
Phase and Estimated Dates Approximate Address
Phase 1 - September 14, 2023 to October 5, 2023 73 to 82 E. Main Street
Phase 2 – September 27, 2023 to November 29, 2023 5 to 73 E. Main Street
Phase 3 – January 4, 2023 to January 22, 2024 4 W. Main Street to 5 E. Main Street
Phase 4 – January 10, 2024 to February 23, 2024 14 to 42 W. Main Street
Phase 5 – November 7, 2023 to January 3, 2024 4 to 14 W. Main Street
Phase 6 – February 5, 2024 to March 21, 2024 42 to 59 W. Main Street
Phase 7 – March 11, 2024 to April 30, 2024 59 to 85 W. Main Street
Phase 8 – April 16, 2024 to June 3, 2024 85 to 107 W. Main Street